A and B can do a piece of work in 36 days. B and C can do the same work in 60 days. A and C can do the same work in 45 days. In how many days can A alone complete the same work?
Watch SolutionA and B can do a piece of work in 6 days and 8 days, respectively. With the help of C, they completed the work in 3 days and earned Rs. 1848. What was the share of C ?
Watch SolutionJoseph deposited a total of ₹52,500 in a bank in names of his two daughters aged 15 years and 16 years in such a way that they would get equal amounts when they become 18 years old. If the bank gives 10% compound interest compounded annually, then what is the amount (in ₹) that Joseph had deposited in the name of his younger daughter?
Watch SolutionIf 4 men and 6 boys can do a work in 8 days and 6 men and 4 boys can do the same work in 7 days, then how many days will 5 men and 4 boys take to do the same work?